From the day the agreement is signed, the solar process typically takes a maximum of three (3) months for a residential project and up to 4-6 months for a commercial one. This allows us time to design and engineer the system, complete all required rebate and utility interconnection paperwork and obtain all permitting from the city. The actual installation crew will be physically on the site for typically 2-4 days for residential installations and 2-4 weeks for commercial solar installations, depending on the system size.